Meeting Date:
|
|
Category:
|
SCHOOL FACILITIES MANAGEMENT |
|
|
Type:
|
|
Subject:
|
16.19 Award of Capital Construction HVAC Work CIP10927 “HVAC Upgrades” at Paideia School 15 to Mengler Mechanical, Inc. for $1,472,000.00 and a term of 365 calendar days. |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Rationale:
|
This resolution is to grant the administration the authority to enter into the subject contract. In compliance with General Municipal Law 103, bids were let and opened in public March 25, 2022. Bid IFB-6743 resulted in a total of 3 bids received, with the highest bid at $1,579,564. The apparent low bidder Ultimate Power, Inc. with bid of $1,215,753 withdrew their bid due to a mathematical error. After interviewing the 2nd low bidder and confirming that they understood the scope of work, their bids were found to be correct, confirmed references, and a successful history with the District, BGA along with this Department is recommending the award of the subject contract to Mengler Mechanical, Inc. The work was designed by Barile Gallagher & Associate Engineers. The HVAC scope of work includes but is not limited to: replacement of the entire chiller plant converting to air cooled chiller, replacement of select unit ventilators, upgrading HVAC digital controls, providing a temporary chiller, and retro-commissioning of all HVAC systems. This work is schedule to start summer of 2022 and be substantially completed by fall of 2022. Bid IFB-6743 resulted in a total of 3 bids received, with the highest bid at $1,579,564. The work was designed by Barile Gallagher & Associate Engineers. The engineer’s estimate for the HVAC work was in the amount of $1.1 million. After interviewing the apparent low bidder and confirming that they understood the scope of work, their bids were found to be correct, confirmed references, and a successful history with the District, BGA along with this Department is recommending the award of the subject contract to Ultimate Power, Inc. The HVAC scope of work includes but is not limited to: replacement of the entire chiller plant converting to air cooled chiller, replacement of select unit ventilators, upgrading HVAC digital controls, providing a temporary chiller, and retro-commissioning of all HVAC systems. This work is schedule to start summer of 2022 and be substantially completed by fall of 2022. |
|
|
Funding:
|
B5515CP110927.B22C02.B2203A1620, $1,472,000.00, LCBF |
|
|
Resolution
|
Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on March 25, 2022 in compliance with General Municipal Law for Bid No. 6743, HVAC Work for CIP 10927 “HVAC Upgrades” at Paideia School 15, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Mengler Mechanical, Inc, is responsive and responsible with a bid of $1,472,000.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6743 HVAC Work, Contract 2, for Capital Project No. 10927 “HVAC Upgrades” at Paideia School 15 to Mengler Mechanical, Inc, 1689 Route 22, Brewster, NY 10509 for a not to exceed amount of $1,427,000.00 for a term of 365 calendar days. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Carr - Executive Director |
|
Signed By: |
|
Tom Collich - Purchasing Director |
|
Signed By: |
|
Finance Department - Finance Reviewer |
|
Signed By: |
|
Elizabeth Janocha - Deputy Commissioner |
|
Signed By: |
|
John Liszewski - Commissioner |
|
Signed By: |
|
Matthew Gallagher - Corporation Counsel |
|
Signed By: |
|
Dr. Edwin M. Quezada - Superintendent of Schools |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Dr. John Castanaro seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on March 25, 2022 in compliance with General Municipal Law for Bid No. 6743, HVAC Work for CIP 10927 “HVAC Upgrades” at Paideia School 15, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Mengler Mechanical, Inc, is responsive and responsible with a bid of $1,472,000.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6743 HVAC Work, Contract 2, for Capital Project No. 10927 “HVAC Upgrades” at Paideia School 15 to Mengler Mechanical, Inc, 1689 Route 22, Brewster, NY 10509 for a not to exceed amount of $1,427,000.00 for a term of 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0. | The motion Carried 8 - 0 | | | Lawrence Sykes | Yes | Rosemarie Linton | Yes | Amjed Kuri | Yes | Gail Burns | Yes | Dr. John Castanaro | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Rev. Steve Lopez | Yes | Kevin Cacace | Yes | |
|
|
|
|
|
|