Meeting Date:
|
2/15/2023 - 5:30 PM
|
Category:
|
SCHOOL FACILITIES MANAGEMENT
|
Type:
|
Action
|
Subject:
|
15.3 Amendment 1 Engineering Design Services on CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School for $1,500.00
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
This is to provide funds to cover the cost of added engineering/design work to remediate unforeseen masonry site conditions which were not present when the project was first in design. This is to authorize Amendment 1 CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School to Eisenbach & Ruhnke Engineering, P.C. (E&R), for $1,500.00 increasing Purchase Order 2022-7860 from $27,500.00 to $29,000.00 and increasing their term by 121 calendar days.
|
Funding:
|
B5547CP110944.B22C02.B2046A1620 $1,500.00 Local Capital Bonded Fund
|
Resolution:
|
Ladies and Gentlemen: WHEREAS: by Resolution Item 15.8 dated March 16, 2022, the Board of Trustees authorized the assignment to Eisenbach & Ruhnke Engineering, P.C. for Architectural/ Engineering services on CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School, and WHEREAS: an amendment is required for additional District directed engineering/design services in the amount of $1,500.00 increasing Purchase Order 2022-7860 from $27,500.00 to $29,000.00 and increasing the term by 121 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend Purchase Order 2022-7860 to Eisenbach & Ruhnke Engineering, P.C., 291 Genesee Street, Utica, New York 13501, for additional engineering services on CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School for an additional $1,500.00 increasing the fee to $29,500.00 and increasing the term by 121 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Michael Pelliccio - Assistant Director of Facilities
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr. Edwin M. Quezada - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Gail Burns seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: by Resolution Item 15.8 dated March 16, 2022, the Board of Trustees authorized the assignment to Eisenbach & Ruhnke Engineering, P.C. for Architectural/ Engineering services on CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School, and WHEREAS: an amendment is required for additional District directed engineering/design services in the amount of $1,500.00 increasing Purchase Order 2022-7860 from $27,500.00 to $29,000.00 and increasing the term by 121 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend Purchase Order 2022-7860 to Eisenbach & Ruhnke Engineering, P.C., 291 Genesee Street, Utica, New York 13501, for additional engineering services on CIP 10944 “Roof Renovations and Related Work” at Robert C. Dodson School for an additional $1,500.00 increasing the fee to $29,500.00 and increasing the term by 121 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0. | The motion Carried 8 - 0 | | | Rosemarie Linton | Yes | Lawrence Sykes | Yes | Sheila Greenwald | Yes | Gail Burns | Yes | Dr. John Castanaro | Yes | Rev. Steve Lopez | Yes | Kevin Cacace | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | |
|
|
|
|
|
|