Subject: 18.3 Amendment of Capital Contracts for Completion
District Goals:
Enclosure
File Attachment:
BOCS 10878 EC NABER.xlsx
BOCS 10878 HV MENGLER.xlsx
Rationale: This is to amend the listed capital contracts by extending their completion dates. This is being done in order to complete work and file necessary paperwork. There are no changes to the funding for these capital projects.
Funding: NOT APPLICABLE
Resolution: WHEREAS the contracted work and paperwork has not yet been completed or submitted and accepted by Yonkers Public Schools, and

WHEREAS the expiration dates for these contracts need to be extended, and

WHEREAS these changes to the capital contracts will extend them accordingly as so listed:

Amendment 1 Contract 2023-00000636, CIP 10878 HVAC work at Westchester Hills School 29, to Mengler Mechanical, Inc. for 365 calendar days revising the contract term from 3-5-2024 to 3-5-2025.

Amendment 2 Contract 2023-00000637, CIP 10878 Electrical work at Westchester Hills School 29, to Naber Electric for 365 calendar days revising the contract term from 3-5-2024 to 3-5-2025.

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to execute these change orders and amendments so listed.
Approvals:
Recommended By:
Signed By:
Michael Pelliccio - Director of Facilities III
Signed By:
Frank Hernandez - Assistant Superintendent
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Anibal Soler, Jr. - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'WHEREAS the contracted work and paperwork has not yet been completed or submitted and accepted by Yonkers Public Schools, and

WHEREAS the expiration dates for these contracts need to be extended, and

WHEREAS these changes to the capital contracts will extend them accordingly as so listed:

Amendment 1 Contract 2023-00000636, CIP 10878 HVAC work at Westchester Hills School 29, to Mengler Mechanical, Inc. for 365 calendar days revising the contract term from 3-5-2024 to 3-5-2025.

Amendment 2 Contract 2023-00000637, CIP 10878 Electrical work at Westchester Hills School 29, to Naber Electric for 365 calendar days revising the contract term from 3-5-2024 to 3-5-2025.

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to execute these change orders and amendments so listed.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0 Abstain: 1.
The motion Carried 5 - 0
   
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Gail Burns     Abstain
Dr. John Castanaro     Yes
Sheila Greenwald     Yes
Amjed Kuri     Yes