Subject: 19.4 CO1 10874 RIVERSIDE SITE WORK VERNON HILLS $61,385.28
District Goals:
Enclosure
File Attachment:
10874 CO LOG - GC SITE - VHCC signed.pdf
RES 23.8 APR 21 2021.pdf
BOCS VERNON GC SITE.xlsx
Rationale: This is to authorize a change order on Contract 5/5 Site Construction, CIP10874 “Interior Renovations, Doors, Security and Site Work” at Riverside High School, to Vernon Hills Contracting Corp., contract 2021-0729 for $61,385.28; increasing the contract from $384,747.00 to $446,132.28.

This change order is result of unforeseen and field conditions, owner directed extra work and design omissions.

Change Orders COP – 02, 03, 07, 11, 15 are considered due to unforeseen field conditions, they include:
• Replacement of gym entry concrete slab in lieu of resurfacing.
• Restoration of collapsed retaining wall.
• Rebuild catch basin not in plan and raise cover
• Modify front plaza with additional slab replacement, additional depth of concrete at proposed replacements, eliminating awkward steps with planter and railing, adding bollards to prevent vehicle parking
• Trenching for new electrical conduit to replace conduit found IN concrete slab during excavation (conduit should be below slabs, not in them)
The total value of unforeseen & field conditions work is $44,904.81

Change Orders COP – 04, 05, 06, 10, 12, 13, 14, 16 are owner directed and include:
• Extend 2 proposed handrails, fabricate one gate, credit for one new rail (walkway A)
• Furnish gate in east railing for fuel oil tank access (walkway B)
• Raise walkway to eliminate trip hazard, add handrail, replace concrete curb at damaged catch basin, install ADA paver marker
• Furnish/install 5 bollards, realign ADA ramp (walkway C, by gym entrance)
• Take credit to delete new precast catch basin (rear roadway)
• Move proposed handrail along walkway D to better protect from the sloped drop in elevation.
• Take credit for providing painted exterior stair nosings in lieu of steel nosings.
The total value of owner directed work is $33,438.60

Change Order COP-01 is considered to be design omission and includes:
• Increase concrete footing size of all/five new exterior light pole bases
The total value of design omission work is $3,041.87.

The amount of extra work is $81,385.28; less the contingency of $20,000.00 a balance change order of $61,385.28 is required with no change in term.
Funding: B5748CP110874.B21C01.B2206A1620 $61,385.28 LCBF
Resolution: Ladies and Gentlemen:

WHEREAS: by Resolution Item No. 23.8 dated April 21, 2021, Contract 2021-0729 was awarded to Vernon Hills Contracting Corp., in the amount of $384,747.00 and for a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed, and

WHEREAS: the fee for this added work is for the negotiated lumps sum price of $61,385.28.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract No. 2021-0729 Contract 5, Site Construction, CIP10874 “Interior Renovations, Doors, Security and Site Work” at Riverside High School, to Vernon Hills Contracting Corp., 315 N. Mac Questen Parkway, Mt. Vernon, NY 10550, for the amount of $61,385.28; increasing the contract amount from $384,747.00 to $446,132.28.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Rosemarie Linton seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: by Resolution Item No. 23.8 dated April 21, 2021, Contract 2021-0729 was awarded to Vernon Hills Contracting Corp., in the amount of $384,747.00 and for a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed, and

WHEREAS: the fee for this added work is for the negotiated lumps sum price of $61,385.28.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract No. 2021-0729 Contract 5, Site Construction, CIP10874 “Interior Renovations, Doors, Security and Site Work” at Riverside High School, to Vernon Hills Contracting Corp., 315 N. Mac Questen Parkway, Mt. Vernon, NY 10550, for the amount of $61,385.28; increasing the contract amount from $384,747.00 to $446,132.28.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Gail Burns     Yes
Sheila Greenwald     Yes
Rosemarie Linton     Yes
Dr. John Castanaro     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes