Review Agenda Item
Meeting Date: 7/21/2021 - 6:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 18.16 CO1 GF FIRE SUPPRESSION HUD VALLEY $28,195.98
District Goals:
Enclosure
File Attachment:
BOCSHudson Valley.xlsx
HV PROPOSAL 7-7-21.pdf
RES 17.8 JUNE 17 2020.pdf
RES 21.23 JUNE 19 2019.pdf
RES 22.18 JUNE 19 2018.pdf
Rationale: CHANGE ORDER 1 TO ANNUAL GENERAL FUND SERVICE CONTRACT to Hudson Valley Fire Protection Systems Contract 2019-0103, PO 2021-02927. The CO is for $28,195.98 increasing the original amount from $57,175 to $85,370.98. Term remains unchanged.

This change order is required for owner directed work in excess of the hours and parts quantities specified in the contract.

Additional repairs to our fire suppression systems required the installation of new “Pyro-chem” 3.0 TO 6.0 gallon fire suppression cylinders throughout the District.
Funding: 450.5150.100000.1625.B2316 Building Repairs $28,195.98
Resolution: Ladies and Gentlemen:

WHEREAS: via Resolution Item No.17.8 dated June 17,2020 the Board amended contract approving the second extension Hudson Valley Fire Protection Systems the Fire Suppression Service Contract, and

WHEREAS: in the course of executing the contracted work it was determined that additional work is required to be performed at various school locations to maintain a safe operable fire suppression system districtwide. These repairs are not exceed $28,195.98 increasing the contract amount from $57,175.00 to $85,370.98.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Hudson Valley Fire Protection Systems, 136 Washington St. Peekskill, N.Y. 10566 for $28,195.98 increasing the contract amount from $57,175.00 to $85,370.98. No change in term.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Dr. John Castanaro seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: via Resolution Item No.17.8 dated June 17,2020 the Board amended contract approving the second extension Hudson Valley Fire Protection Systems the Fire Suppression Service Contract, and

WHEREAS: in the course of executing the contracted work it was determined that additional work is required to be performed at various school locations to maintain a safe operable fire suppression system districtwide. These repairs are not exceed $28,195.98 increasing the contract amount from $57,175.00 to $85,370.98.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Hudson Valley Fire Protection Systems, 136 Washington St. Peekskill, N.Y. 10566 for $28,195.98 increasing the contract amount from $57,175.00 to $85,370.98. No change in term.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0.
The motion Carried 7 - 0
   
Sheila Greenwald     Yes
Gail Burns     Yes
Dr. John Castanaro     Yes
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes