Review Agenda Item
Meeting Date: 11/17/2021 - 6:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 14.4 ASSIGN CIP 10930 LINCOLN HIGH ATHLETIC, SITE & BUILDING DESIGN TO H2M $440,000.00
District Goals:
Enclosure
File Attachment:
RES TABULATION.xlsx
H2M LINCOLN (003).pdf
H2M LINCOLN_Addendum.pdf
H2M YPS_Services_Letter_102021.pdf
Rationale: This is to assign the subject design work for site work at Lincoln High School in response to RFP 420-21-28.

This project is currently expected to cost roughly $8 million. Scope includes new athletic facilities such as artificial turf field, new track and field event features, fencing, signage, security lighting and storage buildings. Other site work includes paving, fencing, sidewalk, etc in parking lots, locker room upgrades and new ceilings and lights in main building hallways.
Funding: B5751CP110930.B21C01.B2046A1620 $440,000.00 LCBF
Resolution: Ladies and Gentlemen:

WHEREAS: under Resolution 15.15 dated February 26, 2020, the Board of Education authorized the award of requirements based, Architectural/Engineering Services Contract No. 2020-0629 to H2M Engineers which expires and will be extended in March of 2022 in response to District RFP404 for an amount not to exceed $1 million and a term of 3 calendar years.

WHEREAS: work as defined under that contract is required for CIP10930 “Building & (Athletic) Site Upgrades” at Lincoln High School, and

WHEREAS:RFP 420-21-28 was issued to procure theses services from the best responder to the RFP, and

WHEREAS: H2M Architects & Engineers provided the best response and the lowest cost proposal at $440,000.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to appoint H2M Architects & Engineers, 538 Broad Hollow Road, 4th Floor East, Melville, NY 11747 to the task of providing A/E services for CIP10930 “Building & (Athletic) Site Upgrades” at Lincoln High School for the amount of $440,000 and a term ending in March 2022.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: under Resolution 15.15 dated February 26, 2020, the Board of Education authorized the award of requirements based, Architectural/Engineering Services Contract No. 2020-0629 to H2M Engineers which expires and will be extended in March of 2022 in response to District RFP404 for an amount not to exceed $1 million and a term of 3 calendar years.

WHEREAS: work as defined under that contract is required for CIP10930 “Building & (Athletic) Site Upgrades” at Lincoln High School, and

WHEREAS:RFP 420-21-28 was issued to procure theses services from the best responder to the RFP, and

WHEREAS: H2M Architects & Engineers provided the best response and the lowest cost proposal at $440,000.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to appoint H2M Architects & Engineers, 538 Broad Hollow Road, 4th Floor East, Melville, NY 11747 to the task of providing A/E services for CIP10930 “Building & (Athletic) Site Upgrades” at Lincoln High School for the amount of $440,000 and a term ending in March 2022.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 9 Nay: 0.
The motion Carried 9 - 0
   
Sheila Greenwald     Yes
Amjed Kuri     Yes
Gail Burns     Yes
Lakisha Collins-Bellamy     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes
Dr. John Castanaro     Yes
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes