Subject: 17.10 Change Order 1 CREDIT 10816 School 9 “Building Renovations & Site Work” HVAC HRR Industries for <$18,910.00> and extending the term for 365 calendar days.
District Goals:
Enclosure
File Attachment:
Res. 23.2 4-21-2021.pdf
Rationale: This is to authorize the execution of the subject change order on Contract 2021-0572 with HRR Industries, Inc., decreasing the contract from $169,000 to $150,090 and extending term for 365 calendar days for paperwork purposes. All work is complete.

By Resolution No. 23.2 dated April 21, 2021, Contract 2021-0572 was awarded to HRR Industries, Inc., in the amount of $169,000 and for a term of 365 calendar days.

Additional work was required to remove and replace deteriorated fin tube radiators in various locations.

The amount of extra work is $18,090.00; less a credit change order of <$12,000.00> and contract contingency of $25,000.00, a CREDIT change order of <$18,910.00> is required.
Funding: B5509CP110816.B21C01.B2203A1620, <$18,910.00>, Local Capital Bonded Fund
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution No. 23.2 dated April 21, 2021, Contract 2021-0572 was awarded to HRR Industries, Inc. in the amount of $169,000.00 and for a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined work was not required to be performed to complete the project for a credit in the amount of <$18,910.00>, decreasing the overall cost of the contract from $169,000.00 to $150,090.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 CREDIT to contract No. 2021-0572 HVAC, Contract 3, CIP10816 “Building Renovations & Site Work” at School 9 to HRR Industries, Inc., 568 North Main Street, Brewster NY10509, for the amount of <$18,910.00>; decreasing the contract amount from $169,000 to $150,090 and extending the contract term for 365 calendar days.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Rosemarie Linton seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution No. 23.2 dated April 21, 2021, Contract 2021-0572 was awarded to HRR Industries, Inc. in the amount of $169,000.00 and for a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined work was not required to be performed to complete the project for a credit in the amount of <$18,910.00>, decreasing the overall cost of the contract from $169,000.00 to $150,090.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 CREDIT to contract No. 2021-0572 HVAC, Contract 3, CIP10816 “Building Renovations & Site Work” at School 9 to HRR Industries, Inc., 568 North Main Street, Brewster NY10509, for the amount of <$18,910.00>; decreasing the contract amount from $169,000 to $150,090 and extending the contract term for 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Amjed Kuri     Yes
Sheila Greenwald     Yes
Rosemarie Linton     Yes
Gail Burns     Yes
Dr. John Castanaro     Yes
Rev. Steve Lopez     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes