Review Agenda Item
Meeting Date: 1/19/2022 - 6:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 15.25 CO1 10812 YMHS NABER ELECTRIC $43,380.61 EXTEND TERM
District Goals:
Enclosure
File Attachment:
COP LOG NABER 11-22-21.pdf
RES 17.18 AUG 19 2020.pdf
BOCS NABER YMHS CO1.xlsx
Rationale: CHANGE ORDER 1 for CAPITAL Contract 2021-0171, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to Naber Electric Corp. for additional work in the amount of $43,380.61; increasing the contract amount from $456,789.00 to $500,169.61 and an extension of the term from 365 to 720 calendar days.


This is a Change Order for unforeseen field conditions including feeder relocation and kitchen exhaust fans operations for $35,157.25 and Omissions including PA wiring and ceiling device relocation for $18,223.36. Total cost of this extra work is $53,380.61.
The change order amount is $53,380.61 less <$10,000.00> allowance for net of $43,380.61.
Funding: B5742CP110812.B20C03.B2205A1620 $4,930.57 LCBF
B5742CP110812.B21C01.B2205A1620 $38,450.04 LCBF
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution 17.18 dated August 19, 2020, Contract No. 2021-0171 CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School was awarded to Naber Electric Corp. for $456,789.00 and a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work was required the added cost of $43,380.61, increasing the contract from $456,789.00 to $500,169.61 and an extension of the term from 365 to 720 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2021-0171, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to Naber Electric Corp. 1025 Saw Mill River Road, Yonkers, NY 10710 in the amount of $43,380.61 increasing the overall cost of the contract from $456,789.00 to $500,169.61 and an extension of the term from 365 to 720 calendar days.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Gail Burns seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution 17.18 dated August 19, 2020, Contract No. 2021-0171 CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School was awarded to Naber Electric Corp. for $456,789.00 and a term of 365 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work was required the added cost of $43,380.61, increasing the contract from $456,789.00 to $500,169.61 and an extension of the term from 365 to 720 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2021-0171, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to Naber Electric Corp. 1025 Saw Mill River Road, Yonkers, NY 10710 in the amount of $43,380.61 increasing the overall cost of the contract from $456,789.00 to $500,169.61 and an extension of the term from 365 to 720 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Rosemarie Linton     Yes
Amjed Kuri     Yes
Sheila Greenwald     Yes
Gail Burns     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes