Subject: 18.32 Abbott & Price, Inc. – Change Order 1
District Goals:
Enclosure
File Attachment:
BOCS CO1 ABBOTT & PRICE.xlsx
Resolution 18.11 August 16 2023 Abbott & Price.pdf
GC Time Extension Request.pdf
Rationale: Abbott & Price, Inc.
Term: Extending contract term 270 calendar days
Amount: $0.00
Scope: Change Order 1 for CIP 10953, 10954, 10955 & 10956, “Playground Upgrades – Part 1 of Playgrounds & Select Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15, extending Contract No. 2024-0244 for an additional term of 270 calendar days.

This resolution is to extend the contract duration for an additional 270 calendars days to complete the work due to rain delays, additional time to complete additional unforeseen work completed under the contract contingency and closeout of paperwork and final payments. This change order does not change the contract amount.
Funding: Not Applicable
Resolution: WHEREAS via Resolution 18.11 dated August 16, 2023, the Board of Education authorized the award of Contract No. 2024-0244 for CIP 10953, 10954, 10955 & 10956, “Playground Upgrades – Part 1 of Playgrounds & Select Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Abbott & Price, Inc. for $1,222,222.00 and a term of 183 calendar days, and

WHEREAS a contract extension of 270 calendar days is required to complete the work, extending the term to 453 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to issue Change Order 1 to Contract No. 2024-0244 for CIP 10953, 10954, 10955 & 10956, “Playground Upgrades – Part 1 of Playgrounds & Select Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Abbott & Price, Inc., extending the contract term 270 calendar days.
Approvals:
Recommended By:
Signed By:
Michael Pelliccio - Director of Facilities III
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Anibal Soler, Jr. - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'WHEREAS via Resolution 18.11 dated August 16, 2023, the Board of Education authorized the award of Contract No. 2024-0244 for CIP 10953, 10954, 10955 & 10956, “Playground Upgrades – Part 1 of Playgrounds & Select Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Abbott & Price, Inc. for $1,222,222.00 and a term of 183 calendar days, and

WHEREAS a contract extension of 270 calendar days is required to complete the work, extending the term to 453 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to issue Change Order 1 to Contract No. 2024-0244 for CIP 10953, 10954, 10955 & 10956, “Playground Upgrades – Part 1 of Playgrounds & Select Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Abbott & Price, Inc., extending the contract term 270 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0.
The motion Carried 6 - 0
   