Agenda Item
Meeting Date:
2/24/2021 - 5:00 PM  
Category:
SCHOOL FACILITIES MANAGEMENT  
Type:
Action  
Subject:
16.7 CHANGE ORDER 2 for CAPITAL Contract 2019-0808, Contract 3 of 4, PLUMBING WORK, CIP10816 “Boiler System Replacement and Asbestos Abatement” at School 9 to Mengler Mechanical, Inc., for the amount of $8,928.05, increasing the contract amount from $357,381.00 to $366,309.05 and extending the contract by 180 calendar days to 545 calendar days.  
District Goals:
 
Enclosure:
 
File Attachment:
BOCS MENGLER P.xlsx
RES 15.24 AUG 21 2019.pdf
RES 20.17 APR 24 2019.pdf
CO LOG MENGLER P.pdf
 
Rationale:
A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, design errors and omissions and owner directed extra work.

Item COP-3-D is for owner directed work and is required to rehabilitate a basement toilet and sanitary line in the amount of $1,709.00.

Items COP-E, F & G are for unforeseen conditions caused by Con-Edison design changes: requiring a gas booster gage to be relocated, new gas pressure regulators be provided for the kitchen equipment and installation of a temporary electric hot water heater while waiting for Con-Ed to install the new gas service. This is in the amount of $7,219.05.
 
Funding:
B5509CP110816.B20C03.B2204A1620, $8,928.05.00, LCBF  
Resolution
Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 20.17 at the Board of Trustees stated meeting on April 24,2019, contract No. 2019-‘0808 was recommended for award to Mengler Mechanical, Inc., 1689 Route 22, Brewster, NY 10509 and,

WHEREAS: by Resolution Item No. 15.24 dated August 21, 2019 Change Order No. 1 in the amount of $7,381.00 increased their contract from $350,000.00 to $357,381.00, and

WHEREAS: in the course of executing the contracted work it was determined that additional work is required to be performed to complete the project in the amount of $8,928.05 increasing the overall cost of the contract from $357,381.00 to $366,309.05, and

WHEREAS a contract extension is required to be extend the contract by 180 calendar days to 545 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 2 to contract No. 2019-0808, PLUMBING WORK, Contract 3, CIP10816 “Boiler System Replacement and Asbestos Abatement” at School 9 to Mengler Mechanical, Inc. for the amount of $8,928.05, increasing the overall cost of the contract from $357,381.00 to $366,309.05 and extending the contract by 180 calendar days to 545 calendar days.
to June 30, 2021.
 
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:  
Tom Collich - Purchasing Director
Signed By:  
Finance Department - Finance Reviewer
Signed By:  
Elizabeth Janocha - Deputy Commissioner
Signed By:  
John Liszewski - Commissioner
Signed By:  
Matthew Gallagher - Corporation Counsel
Signed By:  
Dr. Edwin M. Quezada - Superintendent of Schools
 
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Abdool H. Jamal seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 20.17 at the Board of Trustees stated meeting on April 24,2019, contract No. 2019-‘0808 was recommended for award to Mengler Mechanical, Inc., 1689 Route 22, Brewster, NY 10509 and,

WHEREAS: by Resolution Item No. 15.24 dated August 21, 2019 Change Order No. 1 in the amount of $7,381.00 increased their contract from $350,000.00 to $357,381.00, and

WHEREAS: in the course of executing the contracted work it was determined that additional work is required to be performed to complete the project in the amount of $8,928.05 increasing the overall cost of the contract from $357,381.00 to $366,309.05, and

WHEREAS a contract extension is required to be extend the contract by 180 calendar days to 545 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 2 to contract No. 2019-0808, PLUMBING WORK, Contract 3, CIP10816 “Boiler System Replacement and Asbestos Abatement” at School 9 to Mengler Mechanical, Inc. for the amount of $8,928.05, increasing the overall cost of the contract from $357,381.00 to $366,309.05 and extending the contract by 180 calendar days to 545 calendar days.
to June 30, 2021.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 9 Nay: 0.
The motion Carried 9 - 0
   
Abdool H. Jamal     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Rev. Steve Lopez     Yes
Andrea Brown     Yes
Lakisha Collins-Bellamy     Yes
Dr. John Castanaro     Yes
Sheila Greenwald     Yes
Gail Burns     Yes