Agenda Item
Meeting Date:
1/20/2021 - 5:30 PM  
Category:
SCHOOL FACILITIES MANAGEMENT  
Type:
Action  
Subject:
15.6 ASSIGNMENT OF GENERAL FUND ENGINEERING SERVICES for “Voluntary Potable Water Flushing Program” under Contract 2020-‘0629 to H2M Architects & Engineers in the amount $13,819.50 for a term of 180 calendar days.  
District Goals:
 
Enclosure:
 
File Attachment:
H2M PROP FLUSH.pdf
H2M INV.pdf
 
Rationale:
One of the unintended consequences of the long duration building closures in the spring and summer of 2020 was the stagnation of the domestic water in the building water distribution piping. Out of an abundance of caution, the Department has engaged H2M Architects & Engineers, currently in charge of the District’s “Lead in Water Remediation” program, to oversee building flushing and water sampling & testing to confirm that all water in the buildings was fresh and ready for consumption for the school opening on October 5, 2020.
Their initial proposal was not to exceed $22,500.00. However the actual work was done for $13,819.50.
An RFP was not issued since H2M was most familiar with the building water systems and the work was done on a time and material basis under their current requirements contract, which was awarded under an RFP.
 
Funding:
450.5150.100000.1620.B2300 CONTRACTUAL $13,819.50  
Resolution
Ladies and Gentlemen:
WHEREAS: Via Resolution 15.15, at their stated meeting on February 26, 2020, the Board of Trustees awarded H2M Architects & Engineers, in response to District RFP404 professional services contract #2020-‘0629 for on-call Architectural/Engineering Services for an amount not to exceed $1 million each over a period of three years, and
WHEREAS: work as defined under that contract is required for the 2020 “Voluntary Potable Water Flushing Program” in response to COVID19 building closures, and
WHEREAS: the response by H2M Architects & Engineers to a request for a proposal issued by the Facilities Department was deemed most advantageous to the District at a cost not to exceed $22,500.00, under a time and materials basis, and
WHEREAS: the work entailed was satisfactorily completed at the actual cost of $13,819.50.
NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to assign H2M Architects & Engineers, 538 Broad Hollow Road, 4th Floor East, Melville, NY 11747 to the task of providing engineering services for “Voluntary Potable Water Flushing Program” in response to COVID19 building closures for the final amount of $13,819.50 for a term of 180 calendar days.
 
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:  
Tom Collich - Purchasing Director
Signed By:  
Finance Department - Finance Reviewer
Signed By:  
Elizabeth Janocha - Deputy Commissioner
Signed By:  
John Liszewski - Commissioner
Signed By:  
Matthew Gallagher - Corporation Counsel
Signed By:  
Dr. Edwin M. Quezada - Superintendent of Schools
 
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Gail Burns seconded to approve the Original motion 'Ladies and Gentlemen:
WHEREAS: Via Resolution 15.15, at their stated meeting on February 26, 2020, the Board of Trustees awarded H2M Architects & Engineers, in response to District RFP404 professional services contract #2020-‘0629 for on-call Architectural/Engineering Services for an amount not to exceed $1 million each over a period of three years, and
WHEREAS: work as defined under that contract is required for the 2020 “Voluntary Potable Water Flushing Program” in response to COVID19 building closures, and
WHEREAS: the response by H2M Architects & Engineers to a request for a proposal issued by the Facilities Department was deemed most advantageous to the District at a cost not to exceed $22,500.00, under a time and materials basis, and
WHEREAS: the work entailed was satisfactorily completed at the actual cost of $13,819.50.
NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to assign H2M Architects & Engineers, 538 Broad Hollow Road, 4th Floor East, Melville, NY 11747 to the task of providing engineering services for “Voluntary Potable Water Flushing Program” in response to COVID19 building closures for the final amount of $13,819.50 for a term of 180 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 9 Nay: 0.
The motion Carried 9 - 0
   
Gail Burns     Yes
Sheila Greenwald     Yes
Lakisha Collins-Bellamy     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Abdool H. Jamal     Yes
Dr. John Castanaro     Yes
Kevin Cacace     Yes
Rev. Steve Lopez     Yes
Andrea Brown     Yes