Meeting Date:
|
|
Category:
|
SCHOOL FACILITIES MANAGEMENT |
|
|
Type:
|
|
Subject:
|
19.11 CO1 10825 SCH 17 WINDOWS SITE LANDI GC $11,300.00, EXTEND TERM |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Rationale:
|
This change order is for field conditions and owner directed additional work performed at negotiated lump sum prices. Principally replacing underground damaged roof leaders & restoring deteriorated stone wall $18,900.00, connecting existing manhole to street catch basin $5,500.00, and Owner directed robust security decorative fence and additional chain link fence $15,600.00. Miscellaneous work for $1,300.00 The total net cost of all extra work is $41,300.00, less $30,000.00 in allowance for owner directed work for a total change order of $11,300.00 |
|
|
Funding:
|
B5517CP110825.B19C02.B2200A1620 $11,300.00 Bond Anticipation Note |
|
|
Resolution
|
Ladies and Gentlemen; WHEREAS: via Resolution 16.9 dated March 18, 2020 the Board authorized the award of Contract 2020-0467 CIP 10825 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Peter J.Landi, Inc. for the amount of $868,000.00, and WHEREAS: in the course of construction it was deemed in the best interest of the District to upgrade the security fence, replace deteriorated elements and perform miscellaneous work at the negotiated lump sum prices in the amount of $11,300.00 increasing the contract amount to $879,300.00 and an extension of the term from 546 to 726 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2020-0467 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Peter J.Landi, Inc., 13 Bradhurst Ave, Hawthorne, NY 10532 for the amount of $11,300.00, increasing the total contract amount to $879,300.00 and an extension of the term for 180 calendar days |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Carr - Executive Director |
|
Signed By: |
|
Tom Collich - Purchasing Director |
|
Signed By: |
|
Finance Department - Finance Reviewer |
|
Signed By: |
|
Elizabeth Janocha - Deputy Commissioner |
|
Signed By: |
|
John Liszewski - Commissioner |
|
Signed By: |
|
Matthew Gallagher - Corporation Counsel |
|
Signed By: |
|
Dr. Edwin M. Quezada - Superintendent of Schools |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Rosemarie Linton seconded to approve the Original motion 'Ladies and Gentlemen; WHEREAS: via Resolution 16.9 dated March 18, 2020 the Board authorized the award of Contract 2020-0467 CIP 10825 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Peter J.Landi, Inc. for the amount of $868,000.00, and WHEREAS: in the course of construction it was deemed in the best interest of the District to upgrade the security fence, replace deteriorated elements and perform miscellaneous work at the negotiated lump sum prices in the amount of $11,300.00 increasing the contract amount to $879,300.00 and an extension of the term from 546 to 726 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2020-0467 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Peter J.Landi, Inc., 13 Bradhurst Ave, Hawthorne, NY 10532 for the amount of $11,300.00, increasing the total contract amount to $879,300.00 and an extension of the term for 180 calendar days'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0. | The motion Carried 8 - 0 | | | Rev. Steve Lopez | Yes | Andrea Brown | Yes | Kevin Cacace | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Dr. John Castanaro | Yes | Gail Burns | Yes | Rosemarie Linton | Yes | Sheila Greenwald | Yes | |
|
|
|
|
|
|