Meeting Date:
|
4/19/2023 - 5:30 PM
|
Category:
|
SCHOOL FACILITIES MANAGEMENT
|
Type:
|
Action
|
Subject:
|
19.8 Change Order 1 for CIP 10878 “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” at Westchester Hills School 29 to Talt Electric for $13,000.00 and extend contract term to 180 calendar days
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
By Resolution 16.7 dated April 20, 2022 the Trustees of the Board of Education authorized the award of Contract 2022-0761 for CIP 10878 “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” to Talt Electric for $576,000.00 and a term of 365 calendar days. This is to authorize the award of Change Order 1 in the amount of $13,000.00 increasing the contract to $589,000.00 and extending the term to 180 calendar days. Change Orders COP-5-F is for (Post-bid) NYSED recommended to add Police Notification capacity. This includes conduit, cabling, alarming devices and intercoms. The total value of unforeseen conditions is $6,550.00. Change Orders COP-5-A, C D & E are owner directed extra work and this includes: • Providing temporary power for a temporary trailer for construction management support. • Install electrical conduits and connection boxes for the future generator. • Install conduit, cabling and devices for additional door access control and cameras. The total value of owner directed extra work is $38,500.00. Change Order COP-B & G are considered to be omissions by the AE (disputed). The documents did not include the replacement of a fire alarm pull station and light switch affected by the building renovations. The total value of this work is $2,950.00. The amount of extra work is $48,000.00 and less the contract contingency of $35,000.00, a balance change order of $13,000.00 is required.
|
Funding:
|
B5529CP110878.B22C02.B2205A1620, $13,000.00, Local Capital Bonded Fund
|
Resolution:
|
Ladies and Gentlemen: WHEREAS: By Resolution 16.7 dated April 20, 2022 the Trustees of the Board of Education authorized the award of Contract 2022-0761 for CIP 10878 “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” at Westchester Hills School 29 to Talt Electric for $576,000.00 and a term of 365 calendar days, and WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed, and WHEREAS: the fee for this added work is for the negotiated lump sum price of $48,000.00, and WHEREAS: the contract contingency of $35,000.00 is to be allocated to this change order requiring a balance of $13,000.00 to be covered by additional funds increasing the contract amount from $576,000.00 to $589,000.00, and WHEREAS: a contract extension of 180 calendar days is required to complete the work, extending the term to 545 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2022-0761, CIP 10878, “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” at Westchester Hills School 29 to Talt Electric, 410 Fifth Avenue, New Rochelle, NY 10801 for $13,000.00 increasing the contract from $576,000.00 to $589,000.00 and the term to 545 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Carr - Executive Director
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr. Edwin M. Quezada - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Lawrence Sykes seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: By Resolution 16.7 dated April 20, 2022 the Trustees of the Board of Education authorized the award of Contract 2022-0761 for CIP 10878 “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” at Westchester Hills School 29 to Talt Electric for $576,000.00 and a term of 365 calendar days, and WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed, and WHEREAS: the fee for this added work is for the negotiated lump sum price of $48,000.00, and WHEREAS: the contract contingency of $35,000.00 is to be allocated to this change order requiring a balance of $13,000.00 to be covered by additional funds increasing the contract amount from $576,000.00 to $589,000.00, and WHEREAS: a contract extension of 180 calendar days is required to complete the work, extending the term to 545 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2022-0761, CIP 10878, “Phase I of Roof, Doors, Boiler Systems Replacement and Site Upgrades” at Westchester Hills School 29 to Talt Electric, 410 Fifth Avenue, New Rochelle, NY 10801 for $13,000.00 increasing the contract from $576,000.00 to $589,000.00 and the term to 545 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 9 Nay: 0. | The motion Carried 9 - 0 | | | Kevin Cacace | Yes | Rev. Steve Lopez | Yes | Dr. John Castanaro | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Gail Burns | Yes | Sheila Greenwald | Yes | Amjed Kuri | Yes | Rosemarie Linton | Yes | Lawrence Sykes | Yes | |
|
|
|
|
|
|