Subject: 19.9 CHANGE ORDER 1 10825 SCHOOL 17 WINDOWS & SITE BERTUSSI HVAC $14,657.29, EXTEND TERM
District Goals:
Enclosure
File Attachment:
BOC BERTUSSI.xlsx
COP LOG SIGNED.pdf
RES 15.9 JAN 22 2020.pdf
Rationale: Change Order 1 for Capital Contract 2020-0469 CIP 10825 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Bertussi Contracting Inc. for the amount of $14,657.29 increasing the total contract amount to $157,986.29 and an extension of the term for 180 calendar days.

This change order is for field conditions and owner directed additional work performed at negotiated lump sum prices. Principally for: relocating two exhaust fans $15,922.68, new ductwork for Covid related upgrades $4,108.50, and replacement of deteriorated exhaust ductwork above bathroom ceiling $4,626.11.
Funding: B5517CP110825.B19C02.B2203A1620 $1,562.04 Bond Anticipation Note
B5517CP110825.B21C01.B2203A1620 $13,095.25 Local Capital Bonded Fund
Resolution: Ladies and Gentlemen;
WHEREAS: via Resolution 15.9 dated January 22, 2020 the Board authorized the award of
Contract 2020-0469 CIP 10825 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Bertussi Contracting Inc. for the amount of $143,329.00, and

WHEREAS: in the course of construction it was deemed in the best interest of the District to run new ductwork for Covid related upgrades, and replace deteriorated ductwork for a negotiated amount of $14,657.29 increasing the contract amount from $143,329.00 to $157,986.29 and an extension of the term from 546 to 726 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2020-0469 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to to Bertussi Contracting Inc., 60-70 Dexter Plaza, Pearl River ,NY 10965 for the amount of $14,657.29, increasing the total contract amount to $157,986.29 and an extension of the term for 180 calendar days
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Rosemarie Linton seconded to approve the Original motion 'Ladies and Gentlemen;
WHEREAS: via Resolution 15.9 dated January 22, 2020 the Board authorized the award of
Contract 2020-0469 CIP 10825 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to Bertussi Contracting Inc. for the amount of $143,329.00, and

WHEREAS: in the course of construction it was deemed in the best interest of the District to run new ductwork for Covid related upgrades, and replace deteriorated ductwork for a negotiated amount of $14,657.29 increasing the contract amount from $143,329.00 to $157,986.29 and an extension of the term from 546 to 726 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2020-0469 “Site work, Window Replacement, Interior Renovation and Related Work” at School 17 to to Bertussi Contracting Inc., 60-70 Dexter Plaza, Pearl River ,NY 10965 for the amount of $14,657.29, increasing the total contract amount to $157,986.29 and an extension of the term for 180 calendar days'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Rev. Steve Lopez     Yes
Andrea Brown     Yes
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Dr. John Castanaro     Yes
Rosemarie Linton     Yes
Sheila Greenwald     Yes
Gail Burns     Yes