Subject: 15.11 CO1 CIP10923 EMDEC STORM DAMAGE PEARLS MILCON GC $55,802.89 EXTEND TERM TO 365 DAYS
District Goals:
Enclosure
File Attachment:
EMDEC PEARLS STORM AUG 8 2021.pdf
RES 15.8 SEPT 22 2021.pdf
BOCS MILCON.xlsx
Rationale: Resolution No. 15.8 dated September 22, 2021 awarded Contract 2022-0308 for CIP10923, “Storm Damage Window Stabilization and Repair” at the PEARLS Hawthorne for $150,000.00 and a term of 182 calendar days. This was under the EMDEC by the same name issued by the Superintendent on August 8, 2021.

The initial award of $150,000 was based on an estimate established by the Department. However, the initial estimate of the scope was incomplete. More work was required than originally anticipated. This included roofing, additional masonry work, waterproofing and structural wall work. The cost of this added owner directed work is $55,802.89 increasing the contract amount to $205,802.89 and extending the term to 365 calendar days.
Funding: B5546CP110923.B21C01.B2200A1620, $55,802.89, LCBF
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution No. 15.8 dated August 8, 2021 Contract No. 2022’0308 for CIP10923, “Storm Damage Window Stabilization and Repair” at the PEARLS Hawthorne School was awarded to Milcon Construction Corp for $150,000.00 and a term of 182 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work under “Time and Materials” is required to be performed in the amount of $55,802.89 an the term extended to 365 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract No. 2022-‘0308 CIP10923 “Storm Damage Window Stabilization and Repair” at the PEARLS Hawthorne School under Emergency Declaration to Milcon Construction Corp., 142 Dale Street, Babylon, NY, 11704 for $55,802.89 increasing the contract amount from $150,000.00 to $205,802.89 and extending the term to 365 calendar days.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Gail Burns seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution No. 15.8 dated August 8, 2021 Contract No. 2022’0308 for CIP10923, “Storm Damage Window Stabilization and Repair” at the PEARLS Hawthorne School was awarded to Milcon Construction Corp for $150,000.00 and a term of 182 calendar days, and

WHEREAS: in the course of executing the contracted work it was determined that additional work under “Time and Materials” is required to be performed in the amount of $55,802.89 an the term extended to 365 calendar days.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract No. 2022-‘0308 CIP10923 “Storm Damage Window Stabilization and Repair” at the PEARLS Hawthorne School under Emergency Declaration to Milcon Construction Corp., 142 Dale Street, Babylon, NY, 11704 for $55,802.89 increasing the contract amount from $150,000.00 to $205,802.89 and extending the term to 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Rosemarie Linton     Yes
Amjed Kuri     Yes
Sheila Greenwald     Yes
Gail Burns     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes