18.30 Energy Management of Facilities, Inc.– Amendment 5
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
Energy Management of Facilities, Inc Term: 365 calendar days Amount: $933,600.00 Scope: To authorize Amendment 5 to the General Fund Service Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., (EMF) for $933,600.00. This extension is for the third of five contractually available annual extensions. This is an on-call service as-needed or requirements contract. The vendor performs only as directed by the District.
|
Funding:
|
Pending Adoption of FY2024-25 Budget 450.5150.100000.1620.B2300, Contractual, $383,000.00 450.5150.100000.1625.B2316, Building Repairs, $550,600.00
|
Resolution:
|
WHEREAS via Board Resolution 16.32 dated June 16, 2021, Contract No. 2022-0065 “Maintenance and Repair of HVAC Controls” was awarded to Energy Management of Facilities, Inc., (EMF) for $933,600.00 (with 5 possible extensions) and 365 calendar days, and WHEREAS via Board Resolution 20.29 dated June 14, 2022, this contract was extended for one year (1 of 5 possible extensions), increasing the contract to $1,867,200.00 and the term to 730 calendar days, and WHEREAS via Board Resolution 17.4 dated August 17, 2022, Change Order 1 was issued in the amount of $28,615.25, increasing the contract to $1,895,815.25 with no change in terms, and WHEREAS via Board Resolution 19.30 dated June 21, 2023, this contract was extended for a second time (2 of 5 possible extensions), increasing the contract to $2,829,415.25 and the contract term to 1,095 calendar days, and WHEREAS via Board Resolution 16.17 dated July 19, 2023, Change Order 2 was issued in the amount of $28,720.24, increasing the contract to $2,858,135.49 with no change in terms, and WHEREA there is mutual consent of the parties to extend said contract for the third one-year period (3 of 5 possible extensions). NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to extend Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., for the third time by $933,600.00, increasing the amount to $3,791,735.49 and the term to 1,460 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Michael Pelliccio - Director of Facilities III
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Anibal Soler, Jr. - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'WHEREAS via Board Resolution 16.32 dated June 16, 2021, Contract No. 2022-0065 “Maintenance and Repair of HVAC Controls” was awarded to Energy Management of Facilities, Inc., (EMF) for $933,600.00 (with 5 possible extensions) and 365 calendar days, and WHEREAS via Board Resolution 20.29 dated June 14, 2022, this contract was extended for one year (1 of 5 possible extensions), increasing the contract to $1,867,200.00 and the term to 730 calendar days, and WHEREAS via Board Resolution 17.4 dated August 17, 2022, Change Order 1 was issued in the amount of $28,615.25, increasing the contract to $1,895,815.25 with no change in terms, and WHEREAS via Board Resolution 19.30 dated June 21, 2023, this contract was extended for a second time (2 of 5 possible extensions), increasing the contract to $2,829,415.25 and the contract term to 1,095 calendar days, and WHEREAS via Board Resolution 16.17 dated July 19, 2023, Change Order 2 was issued in the amount of $28,720.24, increasing the contract to $2,858,135.49 with no change in terms, and WHEREA there is mutual consent of the parties to extend said contract for the third one-year period (3 of 5 possible extensions). NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to extend Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., for the third time by $933,600.00, increasing the amount to $3,791,735.49 and the term to 1,460 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0. | The motion Carried 6 - 0 | | | Kevin Cacace | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Gail Burns | Yes | Sheila Greenwald | Yes | Rosemarie Linton | Yes | Felix Rios | Yes | |
|
|
|
|
|
|