Review Agenda Item
Meeting Date: 6/18/2024 - 5:30 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 18.30 Energy Management of Facilities, Inc.– Amendment 5
District Goals:
Enclosure
File Attachment:
2021-6- 16 AWARD RES 16.32.pdf
2022-6- 14 AMENDMENT 1_EXTEND 1 RES 20.29.pdf
2022-8 -17 AMENDMENT 2_CO 1 RES 17.4.pdf
2023-6-21 AMENDMENT 3_EXTEND 2 RES 19.30.pdf
2023-7- 19_AMENDMENT 4_ CO 2 RES 16.17.pdf
Ext. Letter 2024 -2025.pdf
BOCS Amend 5 Extend 3.xlsx
Rationale: Energy Management of Facilities, Inc
Term: 365 calendar days
Amount: $933,600.00
Scope: To authorize Amendment 5 to the General Fund Service Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., (EMF) for $933,600.00.

This extension is for the third of five contractually available annual extensions.

This is an on-call service as-needed or requirements contract. The vendor performs only as directed by the District.
Funding: Pending Adoption of FY2024-25 Budget
450.5150.100000.1620.B2300, Contractual, $383,000.00
450.5150.100000.1625.B2316, Building Repairs, $550,600.00
Resolution: WHEREAS via Board Resolution 16.32 dated June 16, 2021, Contract No. 2022-0065 “Maintenance and Repair of HVAC Controls” was awarded to Energy Management of Facilities, Inc., (EMF) for $933,600.00 (with 5 possible extensions) and 365 calendar days, and

WHEREAS via Board Resolution 20.29 dated June 14, 2022, this contract was extended for one year (1 of 5 possible extensions), increasing the contract to $1,867,200.00 and the term to 730 calendar days, and

WHEREAS via Board Resolution 17.4 dated August 17, 2022, Change Order 1 was issued in the amount of $28,615.25, increasing the contract to $1,895,815.25 with no change in terms, and

WHEREAS via Board Resolution 19.30 dated June 21, 2023, this contract was extended for a second time (2 of 5 possible extensions), increasing the contract to $2,829,415.25 and the contract term to 1,095 calendar days, and

WHEREAS via Board Resolution 16.17 dated July 19, 2023, Change Order 2 was issued in the amount of $28,720.24, increasing the contract to $2,858,135.49 with no change in terms, and

WHEREA there is mutual consent of the parties to extend said contract for the third one-year period (3 of 5 possible extensions).

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to extend Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., for the third time by $933,600.00, increasing the amount to $3,791,735.49 and the term to 1,460 calendar days.
Approvals:
Recommended By:
Signed By:
Michael Pelliccio - Director of Facilities III
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Anibal Soler, Jr. - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'WHEREAS via Board Resolution 16.32 dated June 16, 2021, Contract No. 2022-0065 “Maintenance and Repair of HVAC Controls” was awarded to Energy Management of Facilities, Inc., (EMF) for $933,600.00 (with 5 possible extensions) and 365 calendar days, and

WHEREAS via Board Resolution 20.29 dated June 14, 2022, this contract was extended for one year (1 of 5 possible extensions), increasing the contract to $1,867,200.00 and the term to 730 calendar days, and

WHEREAS via Board Resolution 17.4 dated August 17, 2022, Change Order 1 was issued in the amount of $28,615.25, increasing the contract to $1,895,815.25 with no change in terms, and

WHEREAS via Board Resolution 19.30 dated June 21, 2023, this contract was extended for a second time (2 of 5 possible extensions), increasing the contract to $2,829,415.25 and the contract term to 1,095 calendar days, and

WHEREAS via Board Resolution 16.17 dated July 19, 2023, Change Order 2 was issued in the amount of $28,720.24, increasing the contract to $2,858,135.49 with no change in terms, and

WHEREA there is mutual consent of the parties to extend said contract for the third one-year period (3 of 5 possible extensions).

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to extend Contract No. 2022-0065 for “Maintenance and Repair of HVAC Controls” to Energy Management of Facilities, Inc., for the third time by $933,600.00, increasing the amount to $3,791,735.49 and the term to 1,460 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0.
The motion Carried 6 - 0
   
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Gail Burns     Yes
Sheila Greenwald     Yes
Rosemarie Linton     Yes
Felix Rios     Yes