Review Agenda Item
Meeting Date: 5/17/2023 - 5:30 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 17.13 Change Order 2, CIP 10929 “Cross Hill Academy Fire Restoration” to Milcon Construction Corp, for $17,469.89
District Goals:
Enclosure
File Attachment:
Res. 17.16 7-20-2022.pdf
Res 16.10 3-25-2023.pdf
BOCS CO2 MILCON.xlsx
PCO G Additional Fire Alarm Work.pdf
Rationale: By Resolution 17.16 dated July 20, 2022 Contract 2023-293 CIP 10929 “Cross Hill Academy Fire Restoration” was awarded to Milcon Construction Corp, for $676,400.00 for a term of 365 calendar days. By Resolution 16.10 dated March 15, 2023 Change Order 1 was approved to Milcon Construction Corp., in the amount of $17,757.86 revising the contract to the amount of $694,157.86.

Change Order 2 is required to increase the contract for additional work in the amount of $17,469.89. This added work was not identified in the original bid documents and requires upgrading the school’s existing Fire Alarm system in order to provide fan shut down of the new HVAC equipment upon activation of a fire alarm.

This change order is covered 100% by the District’s insurance carrier, Traveler’s.
Funding: B5534CP110929.B22C01.B2200A1620 $17,469.89 Pending Travelers Insurance Claim
Resolution: Ladies and Gentlemen:

WHEREAS: By Board Resolution 17.16 dated July 20, 2022, Contract No. 2023-293 “Cross Hill Academy Fire Restoration” was awarded to Milcon Construction Corp, for $676,400.00 for a term of 365 calendar days, and

WHEREAS: by Resolution Item 16.10, dated March 15, 2023 Change Order 1 was approved to Milcon Construction Corp., in the amount of $17,757.86; and

WHEREAS: additional work is required to upgrade the School’s Fire Alarm system to support the new HVAC equipment for the negotiated lump sum price of $17,469.89 of which is covered by insurance, increasing the contract from $694,157.86 to $711,627.75.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 2 to Contract 2023-0293 CIP 10929 “Cross Hill Academy Fire Restoration” to Milcon Construction Corp, 142 Dale Street, W. Babylon, NY 11704 for the amount of $17,469.89; increasing the contract amount from $694,157.86 to $711,627.75 and no change in contract term.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Sheila Greenwald seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: By Board Resolution 17.16 dated July 20, 2022, Contract No. 2023-293 “Cross Hill Academy Fire Restoration” was awarded to Milcon Construction Corp, for $676,400.00 for a term of 365 calendar days, and

WHEREAS: by Resolution Item 16.10, dated March 15, 2023 Change Order 1 was approved to Milcon Construction Corp., in the amount of $17,757.86; and

WHEREAS: additional work is required to upgrade the School’s Fire Alarm system to support the new HVAC equipment for the negotiated lump sum price of $17,469.89 of which is covered by insurance, increasing the contract from $694,157.86 to $711,627.75.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 2 to Contract 2023-0293 CIP 10929 “Cross Hill Academy Fire Restoration” to Milcon Construction Corp, 142 Dale Street, W. Babylon, NY 11704 for the amount of $17,469.89; increasing the contract amount from $694,157.86 to $711,627.75 and no change in contract term.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Amjed Kuri     Yes
Rosemarie Linton     Yes
Lawrence Sykes     Yes
Sheila Greenwald     Yes
Gail Burns     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Rev. Steve Lopez     Yes