Meeting Date:
|
3/21/2024 - 5:30 PM
|
Category:
|
SCHOOL FACILITIES MANAGEMENT
|
Type:
|
Action
|
Subject:
|
16.11 Award - Fran Corp (dba-All Bright Electric) - $627,000.00
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
Fran Corp (d/b/a All Bright Electric) Term: 548 calendar days Amount: $627,000.00 Scope: Electrical construction contract work at Martin Luther King Jr. Academy includes; lighting replacement for Main Offices, Main Entrance Corridor; power work for all classroom window AC Units; exterior lighting improvements; power work for the Main Office, Main Entrance Corridor and Cafeteria HVAC upgrades; new High-Tech Security and alternate bid work for kitchen lighting replacement. Overview: In compliance with General Municipal Law 103, bids were let and opened in public on February 15, 2024. Two (2) bids were received, examined and all due diligence observed in determining that Fran Corp (d/b/a All Bright Electric) is the lowest responsive and responsible bidder. The work was designed by Eisenbach & Ruhnke Engineering, P.C. who estimated the value of the work at $1,271,500. The highest bid was $987,888.
|
Funding:
|
B5533CP110875.B24C01.B2205A1620, $627,000.00, Local Capital Bonded Fund
|
Resolution:
|
WHEREAS bids were issued for public advertisement and opened on February 15, 2024 in compliance with General Municipal Law 103 for Bid No. 7084 ELECTRICAL Work, (Contract 4) for the “Roof Replacement and Select Interior Upgrades - Roof, Heating Plant, Window Replacement and Interior Upgrades” at Martin Luther King, Jr. Academy, Project No. 10875, and WHEREAS such bids were duly examined and as a result the administration has determined that Fran Corp (d/b/a All Bright Electric) is the lowest responsive and responsible bidder with a bid of $627,000.00. NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to award Bid No. 7084 ELECTRICAL Work, (Contract 4), for Project No. 10875 “Roof Replacement and Select Interior Upgrades - Roof, Heating Plant, Window Replacement and Interior Upgrades” at Martin Luther King,
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Michael Pelliccio - Director of Facilities III
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr. Luis Rodriguez - Interim Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Amjed Kuri seconded to approve the Original motion 'WHEREAS bids were issued for public advertisement and opened on February 15, 2024 in compliance with General Municipal Law 103 for Bid No. 7084 ELECTRICAL Work, (Contract 4) for the “Roof Replacement and Select Interior Upgrades - Roof, Heating Plant, Window Replacement and Interior Upgrades” at Martin Luther King, Jr. Academy, Project No. 10875, and WHEREAS such bids were duly examined and as a result the administration has determined that Fran Corp (d/b/a All Bright Electric) is the lowest responsive and responsible bidder with a bid of $627,000.00. NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to award Bid No. 7084 ELECTRICAL Work, (Contract 4), for Project No. 10875 “Roof Replacement and Select Interior Upgrades - Roof, Heating Plant, Window Replacement and Interior Upgrades” at Martin Luther King,'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Kevin Cacace | Yes | Rev. Steve Lopez | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Amjed Kuri | Yes | Rosemarie Linton | Yes | |
|
|
|
|
|
|