14.9 CHANGE ORDER 1 (CREDIT) for CAPITAL Contract 2019-00000886, Contract 2 of 3, HVAC WORK, CIP10817 “Windows, Doors, Site and Security Improvements” at William Boyce Thompson School to Best Climate Control, for a credit in the amount of $10,000, decreasing the contract amount from $42,000 to $32,000. |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Rationale:
|
A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, design errors and omissions and owner directed extra work. This is a credit Change Order of $10,000.00 for the entire remaining balance to a $10,000.00 allowance of any additional work in the contract. There was no owner requested extra work in this contract. |
|
|
Funding:
|
B5507CP110817.B18C01.B2203A1620 -$10,000.00 LCBF CREDIT |
|
|
Resolution
|
Ladies and Gentlemen: WHEREAS by Resolution Board Item No. 20.11 at the Board of Trustees stated meeting on May 15, 2019, Contract No. 2019-00000886 was recommended for award to Best Climate Control, 75 Orville Drive, Bohemia, NY 11716 and, WHEREAS: in the course of executing the contracted work it was determined that additional allowance work was not required to be performed for a credit in the amount of $10,000.00, decreasing the overall cost of the contract from $42,000.00 to $32,000.00. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2019-00000886, HVAC Construction Contract, CIP10817, “Windows, Doors, Site and Security Improvements” at William Boyce Thompson School to Best Climate Control for a CREDIT in the amount of $10,000.00, decreasing the overall cost of the contract from $42,000.00 to $32,000.00. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Carr - Executive Director |
|
Signed By: |
|
Tom Collich - Purchasing Director |
|
Signed By: |
|
Finance Department - Finance Reviewer |
|
Signed By: |
|
Elizabeth Janocha - Deputy Commissioner |
|
Signed By: |
|
John Liszewski - Commissioner |
|
Signed By: |
|
Matthew Gallagher - Corporation Counsel |
|
Signed By: |
|
Dr. Edwin M. Quezada - Superintendent of Schools |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Judith_Ramos Meier seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS by Resolution Board Item No. 20.11 at the Board of Trustees stated meeting on May 15, 2019, Contract No. 2019-00000886 was recommended for award to Best Climate Control, 75 Orville Drive, Bohemia, NY 11716 and, WHEREAS: in the course of executing the contracted work it was determined that additional allowance work was not required to be performed for a credit in the amount of $10,000.00, decreasing the overall cost of the contract from $42,000.00 to $32,000.00. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2019-00000886, HVAC Construction Contract, CIP10817, “Windows, Doors, Site and Security Improvements” at William Boyce Thompson School to Best Climate Control for a CREDIT in the amount of $10,000.00, decreasing the overall cost of the contract from $42,000.00 to $32,000.00.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0. | The motion Carried 8 - 0 | | | Lakisha Collins-Bellamy | Yes | Dr. John Castanaro | Yes | Abdool H. Jamal | Yes | Kevin Cacace | Yes | Andrea Brown | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Rev. Steve Lopez | Yes | Judith_Ramos Meier | Yes | |
|
|
|
|
|
|