15.15 CO1 10812 YMHS GC WORK APS $74,905.66 EXTEND TERM |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Rationale:
|
CHANGE ORDER 1 for CAPITAL GENERAL CONSTRUCTION Contract 2021-00000168, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to APS Contracting, Inc. in the amount of $74,905.66; increasing the contract amount from $1,573,000.00 to $1,647,905.66 and an extension of the term from 365 to 720 calendar days. This Change Order is to for owner directed extra work to address field conditions and contract omissions. This includes: • Masonry work: chimney, walls, & stairways for roughly $60,000.00. • New chimney caps $15,697.50 • Classroom furniture for $34,246.29 from School Specialty Furniture via NYSOGS contract Group 20915 - Award 23109. • Upgraded windows, repair and paint exterior railings, demolition of water proofing membranes for $30, 803.18. Total cost for CO1 is $132,950.70; less <$43,045.00> credit for deducted work, less <$15,000.00> allowance is $74,905.66 |
|
|
Funding:
|
B5742CP110812.101256.B2200 $2,531.74 LCBF B5742CP110812.B20C03.B2200A1620 $72,373.92 LCBF |
|
|
Resolution
|
Ladies and Gentlemen: WHEREAS: by Resolution 17.8 dated August 19, 2020, Contract No. 2021 0168 CIP 10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to APS Contracting f or $1,573,000.00 and a term of 365 calendar days, and WHEREAS: in the course of executing the contracted work it was determined that additional work was required the added cost of $74,905.66, increasing the contract to $1,573,000.00 to $1,647,905.66 and an extension of the term from 365 to 720 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2021-0168, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to APS Contracting, Inc., 155-161 Pennsylvania Avenue Paterson, NJ 07503 in the amount of $74,905.66 increasing the overall cost of the contract from $1,573,000.00 to $1,647,905.66 and an extension of the term from 365 to 720 calendar days. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Carr - Executive Director |
|
Signed By: |
|
Tom Collich - Purchasing Director |
|
Signed By: |
|
Finance Department - Finance Reviewer |
|
Signed By: |
|
Elizabeth Janocha - Deputy Commissioner |
|
Signed By: |
|
John Liszewski - Commissioner |
|
Signed By: |
|
Matthew Gallagher - Corporation Counsel |
|
Signed By: |
|
Dr. Edwin M. Quezada - Superintendent of Schools |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Gail Burns seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: by Resolution 17.8 dated August 19, 2020, Contract No. 2021 0168 CIP 10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to APS Contracting f or $1,573,000.00 and a term of 365 calendar days, and WHEREAS: in the course of executing the contracted work it was determined that additional work was required the added cost of $74,905.66, increasing the contract to $1,573,000.00 to $1,647,905.66 and an extension of the term from 365 to 720 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2021-0168, CIP10812 “Reconstruction of Portions of the Building” at Yonkers Middle High School to APS Contracting, Inc., 155-161 Pennsylvania Avenue Paterson, NJ 07503 in the amount of $74,905.66 increasing the overall cost of the contract from $1,573,000.00 to $1,647,905.66 and an extension of the term from 365 to 720 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0. | The motion Carried 8 - 0 | | | Rosemarie Linton | Yes | Amjed Kuri | Yes | Sheila Greenwald | Yes | Gail Burns | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Kevin Cacace | Yes | Andrea Brown | Yes | Rev. Steve Lopez | Yes | |
|
|
|
|
|
|