Subject: 15.5 Fuller and D’Angelo, P.C. Architects & Planners (CIP 10955) – Amendment 2
District Goals:
Enclosure
File Attachment:
Res. 15.6 11-16-2022.pdf
F&D Proposal EmDec PS29 Ball Field Washout.pdf
ED 29 Ball Field Washout.pdf
Rationale: Fuller & D’Angelo Architects & Planners, P.C.
Term: No change in term
Amount: $10,000.00
Scope: To provide architectural services for the restoration of the Westchester Hills School 29 Ball Field Washout under Emergency Declaration.

Overview:
To assign Fuller & D’Angelo Architects & Planners, P.C. (F&D) under their existing “On-Call” Architectural Service Contract No. 2020-0628, for restoration of the Westchester Hills School 29 Ball Field Washout under Emergency Declaration. F&D will provide the designs, SED filing, bidding and construction administration services under a time & material basis. The emergency project will be filed with NYSED as an addendum to the existing Capital Project 10955, “Playground & Select Building Upgrades” at Westchester Hills School 29.

The construction restoration of the ball field washout is estimated to be in the amount of $80,000.00.
Funding: $10,000.00
Bond Anticipation Note
B5529CP110955.B19C02.B2046A1620
Resolution: WHEREAS Via Resolution 15.6 dated November 16, 2022, the Board of Education awarded PO 2023-4875 Architectural Services for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to F&D in the amount of $215,560.00 and a term of 365 calendar days under Contract 2020-0628, and

WHEREAS additional architectural services are required for the emergency restoration of the ball field washout at the Westchester Hills School 29, and

WHEREAS F&D has presented an acceptable proposal to complete this added task for Design, Filling, Bidding & Construction Administration Services for the Playground Work at a cost of $10,000.00, and

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to amend the existing assignment for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 under Contract 2020-0628 to Fuller & D’Angelo P.C. for $10,000.00, increasing the amount from $250,260.00 to $260,260.00 with no change in term.
Approvals:
Recommended By:
Signed By:
Michael Pelliccio - Director of Facilities III
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Luis Rodriguez - Interim Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Amjed Kuri seconded to approve the Original motion 'WHEREAS Via Resolution 15.6 dated November 16, 2022, the Board of Education awarded PO 2023-4875 Architectural Services for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to F&D in the amount of $215,560.00 and a term of 365 calendar days under Contract 2020-0628, and

WHEREAS additional architectural services are required for the emergency restoration of the ball field washout at the Westchester Hills School 29, and

WHEREAS F&D has presented an acceptable proposal to complete this added task for Design, Filling, Bidding & Construction Administration Services for the Playground Work at a cost of $10,000.00, and

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to amend the existing assignment for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 under Contract 2020-0628 to Fuller & D’Angelo P.C. for $10,000.00, increasing the amount from $250,260.00 to $260,260.00 with no change in term.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0.
The motion Carried 7 - 0
   
Rev. Steve Lopez     Yes
Kevin Cacace     Yes
Gail Burns     Yes
Sheila Greenwald     Yes
Amjed Kuri     Yes
Rosemarie Linton     Yes
Lawrence Sykes     Yes